ADU cost in Clairemont, San Diego (2026 permit data)

How much does an ADU cost in Clairemont?

Single-ADU permits near Clairemont declared a median $146,100 of construction in 2026 (middle half $89,900–$175,700, 61 permits), 21% above the City of San Diego median of $120,900. Declared value excludes design, City fees and utility work.

Source: City of San Diego permit data (data.sandiego.gov), permits issued Jan 1–Oct 15, 2026. Area = permits within about 1.6 miles of the neighborhood center. Last updated: . Methodology

99 City building permits near Clairemont added at least one ADU between January 1 and October 15, 2026. Of these, 27 were conversions and 22 new detached units, so Clairemont leans toward conversions.

Planning range for a premium build: start from the $175,700 upper quartile and add design, engineering, utility connections and finishes.

Compare up to 3 vetted local builders

Quick fit check, 3 taps. Helps us match you with a top-rated pro.
Free & no obligation. About 1 minute.

Clairemont ADU permits by type

TypePermitsLow (25%)MedianHigh (75%)
All single-ADU permits61$89,900$146,100$175,700
Conversions (garage/room)27$85,300$128,700$149,900
New detached ADUs22$128,700$153,300$190,700
City of San Diego, all areas750$76,000$120,900$197,700

Valuation is the construction value declared to the City, not a quote. Download the area data.

Permit timeline in Clairemont

The median ADU permit near Clairemont took 315 days from application to issue, versus 298 days citywide. Correction rounds are usually the longest part. Full timeline · Step-by-step permit guide.

How an ADU project runs

  1. Feasibility (1–3 weeks): lot, setbacks, sewer lateral, panel capacity.
  2. Design and engineering (1–3 months).
  3. City plan check and corrections (315 days median here, application to issue).
  4. Construction: conversions are generally shorter than new detached builds.
  5. Final inspection, utilities, occupancy. A panel upgrade often follows; see what comes next.

Questions San Diego homeowners ask

What is the typical ADU budget in Clairemont?

Single-ADU permits near Clairemont declared a median $146,100 of construction in 2026 (middle half $89,900–$175,700, 61 permits), 21% above the City of San Diego median of $120,900. Declared value excludes design, City fees and utility work.

Is a garage conversion cheaper than a detached ADU in Clairemont?

Near Clairemont, conversions declared a median $128,700 (27 permits) and new detached ADUs $153,300 (22 permits). See the full comparison.

How long does an ADU permit take in Clairemont?

The 2026 median near Clairemont was 315 days from application to issue (298 days citywide).

Are City impact fees charged on ADUs?

Development Impact Fees are waived for ADUs under 750 sq ft and for the first two ADUs on a property (SDMC §142.0640). School, plan check and permit fees still apply.

Ready to price your Clairemont ADU?

We match serious homeowners with up to 3 licensed, well-reviewed builders who work in your area. Free, no obligation.

Start your request →

Other areas: College Area · City Heights · North Park · Mira Mesa · Pacific Beach · South Park & Golden Hill · Encanto · Bay Park · La Jolla · Point Loma · Kensington & Talmadge · Hillcrest & Mission Hills · Linda Vista · Paradise Hills

SD Price Hub network: real San Diego price data

Get free ADU quotes