ADU cost in Hillcrest & Mission Hills, San Diego (2026 permit data)

How much does an ADU cost in Hillcrest & Mission Hills?

Single-ADU permits near Hillcrest & Mission Hills declared a median $106,600 of construction in 2026 (middle half $61,800–$235,000, 22 permits), 12% below the City of San Diego median of $120,900. Declared value excludes design, City fees and utility work.

Source: City of San Diego permit data (data.sandiego.gov), permits issued Jan 1–Oct 15, 2026. Area = permits within about 1.6 miles of the neighborhood center. Last updated: . Methodology

35 City building permits near Hillcrest & Mission Hills added at least one ADU between January 1 and October 15, 2026. Of these, 9 were conversions and 8 new detached units, so Hillcrest & Mission Hills leans toward conversions.

Planning range for a premium build: start from the $235,000 upper quartile and add design, engineering, utility connections and finishes.

Compare up to 3 vetted local builders

Quick fit check, 3 taps. Helps us match you with a top-rated pro.
Free & no obligation. About 1 minute.

Hillcrest & Mission Hills ADU permits by type

TypePermitsLow (25%)MedianHigh (75%)
All single-ADU permits22$61,800$106,600$235,000
Conversions (garage/room)9$61,600$66,300$127,700
New detached ADUs8$67,100$172,800$226,400
City of San Diego, all areas750$76,000$120,900$197,700

Valuation is the construction value declared to the City, not a quote. Download the area data.

Permit timeline in Hillcrest & Mission Hills

The median ADU permit near Hillcrest & Mission Hills took 318 days from application to issue, versus 298 days citywide. Correction rounds are usually the longest part. Full timeline · Step-by-step permit guide.

How an ADU project runs

  1. Feasibility (1–3 weeks): lot, setbacks, sewer lateral, panel capacity.
  2. Design and engineering (1–3 months).
  3. City plan check and corrections (318 days median here, application to issue).
  4. Construction: conversions are generally shorter than new detached builds.
  5. Final inspection, utilities, occupancy. A panel upgrade often follows; see what comes next.

Questions San Diego homeowners ask

What is the typical ADU budget in Hillcrest & Mission Hills?

Single-ADU permits near Hillcrest & Mission Hills declared a median $106,600 of construction in 2026 (middle half $61,800–$235,000, 22 permits), 12% below the City of San Diego median of $120,900. Declared value excludes design, City fees and utility work.

Is a garage conversion cheaper than a detached ADU in Hillcrest & Mission Hills?

Near Hillcrest & Mission Hills, conversions declared a median $66,300 (9 permits) and new detached ADUs $172,800 (8 permits). See the full comparison.

How long does an ADU permit take in Hillcrest & Mission Hills?

The 2026 median near Hillcrest & Mission Hills was 318 days from application to issue (298 days citywide).

Are City impact fees charged on ADUs?

Development Impact Fees are waived for ADUs under 750 sq ft and for the first two ADUs on a property (SDMC §142.0640). School, plan check and permit fees still apply.

Ready to price your Hillcrest & Mission Hills ADU?

We match serious homeowners with up to 3 licensed, well-reviewed builders who work in your area. Free, no obligation.

Start your request →

Other areas: College Area · City Heights · Clairemont · North Park · Mira Mesa · Pacific Beach · South Park & Golden Hill · Encanto · Bay Park · La Jolla · Point Loma · Kensington & Talmadge · Linda Vista · Paradise Hills

SD Price Hub network: real San Diego price data

Get free ADU quotes