ADU cost in Kensington & Talmadge, San Diego (2026 permit data)

How much does an ADU cost in Kensington & Talmadge?

Single-ADU permits near Kensington & Talmadge declared a median $95,100 of construction in 2026 (middle half $56,700–$129,900, 23 permits), 21% below the City of San Diego median of $120,900. Declared value excludes design, City fees and utility work.

Source: City of San Diego permit data (data.sandiego.gov), permits issued Jan 1–Oct 15, 2026. Area = permits within about 1.6 miles of the neighborhood center. Last updated: . Methodology

37 City building permits near Kensington & Talmadge added at least one ADU between January 1 and October 15, 2026. Of these, 16 were conversions and 5 new detached units, so Kensington & Talmadge leans toward conversions.

Planning range for a premium build: start from the $129,900 upper quartile and add design, engineering, utility connections and finishes.

Compare up to 3 vetted local builders

Quick fit check, 3 taps. Helps us match you with a top-rated pro.
Free & no obligation. About 1 minute.

Kensington & Talmadge ADU permits by type

TypePermitsLow (25%)MedianHigh (75%)
All single-ADU permits23$56,700$95,100$129,900
Conversions (garage/room)16$49,700$73,200$122,400
New detached ADUs5$86,700$187,400$214,500
City of San Diego, all areas750$76,000$120,900$197,700

Valuation is the construction value declared to the City, not a quote. Download the area data.

Permit timeline in Kensington & Talmadge

The median ADU permit near Kensington & Talmadge took 280 days from application to issue, versus 298 days citywide. Correction rounds are usually the longest part. Full timeline · Step-by-step permit guide.

How an ADU project runs

  1. Feasibility (1–3 weeks): lot, setbacks, sewer lateral, panel capacity.
  2. Design and engineering (1–3 months).
  3. City plan check and corrections (280 days median here, application to issue).
  4. Construction: conversions are generally shorter than new detached builds.
  5. Final inspection, utilities, occupancy. A panel upgrade often follows; see what comes next.

Questions San Diego homeowners ask

What is the typical ADU budget in Kensington & Talmadge?

Single-ADU permits near Kensington & Talmadge declared a median $95,100 of construction in 2026 (middle half $56,700–$129,900, 23 permits), 21% below the City of San Diego median of $120,900. Declared value excludes design, City fees and utility work.

Is a garage conversion cheaper than a detached ADU in Kensington & Talmadge?

Near Kensington & Talmadge, conversions declared a median $73,200 (16 permits) and new detached ADUs $187,400 (5 permits). See the full comparison.

How long does an ADU permit take in Kensington & Talmadge?

The 2026 median near Kensington & Talmadge was 280 days from application to issue (298 days citywide).

Are City impact fees charged on ADUs?

Development Impact Fees are waived for ADUs under 750 sq ft and for the first two ADUs on a property (SDMC §142.0640). School, plan check and permit fees still apply.

Ready to price your Kensington & Talmadge ADU?

We match serious homeowners with up to 3 licensed, well-reviewed builders who work in your area. Free, no obligation.

Start your request →